City of Bremerton
Material Testing Services for Central Bremerton Force Main Replacement Project
197
Category
Public Works & Utilities
Description
The work to be performed by the CONSULTANT consists of sampling and testing materials for improvements to the following project. Materials that may be sampled and tested included asphalt, crushed aggregate and concrete:Central Bremerton Force Main Replacement Project: Construction of 3,100 lf of 14-inch and 18-inch PVC sewer force main, construction of new sections of sidewalk and curb ramps at isolated locations, storm sewer relocation and replacement, removal of stumps and trees at 1912 Gregory Way, replacement of a surge chamber at Gregory Way and High Street, a sewer bypass and pavement patch in the intersection of Burwell and Warren Avenue, and planing and repaving 1st street from South Mongomery Avenue to Naval Avenue.The construction project will begin in July 2025 and end in November 2025.
Important Dates
Publication Date
5/23/2025
Closing Date
6/12/2025
Timeline
Publication date5/23/2025
Closing date6/12/2025
Construction start7/1/2025
Construction end11/30/2025
Location
1912 Gregory Way
Bremerton, WA
Submission Requirements
Bid submissions for Material Testing Services; see Related Documents for Bid Set, Bid Drawings, and RFQ/RFP PDFs. Responses due by the Closing Date.
Submission Deadline: 6/12/2025
Documents
Contact Information
Additional Information
Publication
Publication Date/Time: 2025-05-23 12:00 AM; Closing Date/Time: 2025-06-12 12:00 PM
Project Details
Construction start: July 2025; Construction end: November 2025. Construction includes 3,100 lf of 14-inch and 18-inch PVC sewer force main, sidewalk/curb ramp work, storm sewer work, stump removal, surge chamber replacement, sewer bypass, pavement patch at Burwell/Warren, and repaving 1st Street from South Mongomery Avenue to Naval Avenue.