Project Timeline
Release Project Date
Wednesday, January 14, 2026 at 5:29 PM
Mandatory Pre-Proposal Meeting Option 1 (must attend at least one)
Thursday, January 22, 2026 at 7:00 PM
Location: Please meet on the walkway near the northeast corner of the International Fountain Mall.
Question Submission Deadline
Friday, February 6, 2026 at 1:00 AM
Bid Open Date
Wednesday, February 11, 2026 at 10:00 PM
Additional Timeline Information
{
"id": 105730,
"title": "Mandatory Pre-Proposal Meeting Option 2 (must attend at least one) ",
"date": "2026-01-29T18:00:28.894Z",
"displayTime": true,
"hasTextDate": false,
"textDate": null,
"showLocation": true,
"location": "Please meet on the walkway near the northeast corner of the International Fountain Mall.",
"agendaUrl": null,
"isAttendanceRequired": false,
"isPublic": true,
"isRsvpEnded": false,
"orderById": 3,
"created_at": "2026-01-13T17:33:48.695Z",
"updated_at": "2026-01-13T21:24:23.28Z",
"project_id": 228450
}