Release Project Date
Wednesday, April 29, 2026 at 7:00 AM
Question Submission Deadline
Friday, May 15, 2026 at 12:00 AM
Bid Open Date
Wednesday, May 20, 2026 at 9:00 PM
Additional Timeline Information
{
"id": 118687,
"title": "Pre-Bid Meeting #1 (Mandatory for Bidders to attend at least 1 of the 2 Pre-Bid Meetings)",
"date": "2026-05-05T17:00:00Z",
"displayTime": true,
"hasTextDate": false,
"textDate": null,
"showLocation": true,
"location": "at the intersection of 8th Ave S and S Chicago St, Seattle, WA 98108",
"agendaUrl": null,
"isAttendanceRequired": false,
"isPublic": false,
"isRsvpEnded": false,
"orderById": 2,
"created_at": "2026-04-22T22:07:51.491Z",
"updated_at": "2026-04-22T22:07:51.491Z",
"project_id": 258854
}{
"id": 118686,
"title": "Pre-Bid Meeting #2 (Mandatory for Bidders to attend at least 1 of the 2 Pre-Bid Meetings)",
"date": "2026-05-07T18:00:00Z",
"displayTime": true,
"hasTextDate": false,
"textDate": null,
"showLocation": true,
"location": "at the intersection of 8th Ave S and S Chicago St, Seattle, WA 98108",
"agendaUrl": null,
"isAttendanceRequired": false,
"isPublic": false,
"isRsvpEnded": false,
"orderById": 3,
"created_at": "2026-04-22T22:07:51.492Z",
"updated_at": "2026-04-22T22:09:50.42Z",
"project_id": 258854
}